hierzu: Prairie Wind Energy, LLC is authorized to construct and operate up to a 100 Megawatt Large Wind Energy Conversion System http://www.energyfacilities.puc.state.mn.us/...-10-438_Commission.pdf October 7, 2011 • Minnesota Windy debate hits Parkers Prairie
"The Project is a Large Energy Facility as defined in Minn. Stat. § 216B.2421, Subd. 2, and cannot be constructed without a Certificate of Need (CN) from the Minnesota Public Utilities Commission. " http://energyfacilities.puc.state.mn.us/Docket.html?Id=30591 http://energyfacilities.puc.state.mn.us/Docket.html?Id=30591 z.B. da http://www.wallstreet-online.de/diskussion/...giewende-nach-fukushima STATE OF MINNESOTA PUBLIC UTILITIES COMMISSION February 3,2012 NOTICE OF COMMISSION MEETING PLEASE TAKE NOTICE that the items listed on the attached agenda will be heard at the Commission's regularly scheduled meeting on Thursday February 16, 2012 at 9:30 AM. 8 IP6844/CN-10-429 Prairie Wind Energy, LLC In the Matter of the Application of Prairie Wind Energy, LLC for a Certificate ofNeed for the 100MW Wind Project in Otter Tail County. Should the Commission find that the Environmental Report on this project adequately addresses the scoping decision ofthe Director ofthe Department of Commerce Division of Energy Resources? Should the Commission grant a certificate of need for the proposed Prairie Wind Project? (PUC: Kaluzniak)
9 IP6844/WS-10-438 Prairie Wind Energy, LLC In the Matter ofthe ApplicationofPrairieWindEnergy,LLC for a LargeWindEnergy Conversion System Site Permitfor the 100MWPrairieWindEnergy Project in Otter Tail County. Should the Commission grant a site permit to PrairieWindEnergy, LLCfor the 100MW Prairie WindEnergyProject? (PUC: Kaluzniak; DOC; Birkholz https://www.edockets.state.mn.us/EFiling/edockets/...e=20122-70994-06 da geht es jetzt dann wohl um die final site permit?... http://www.ariva.de/forum/Nordex-Akte-X-442705?page=246 "PWE currently anticipates that the Project would consist of 41 2.4 MW Nordex N117 turbines yielding a total nameplate capacity of 98.4 MW. The Applicant however is requesting authority for a total nameplate capacity of 100 MW, allowing the final number and size of the turbines to be dictated by the terms of a Power Purchase Agreement (PPA) between PWE and an off-taker, current market conditions, turbine availability and the terms of the final Site Permit for the Project." |