in den Jahren seit Erwerb der Konzession an der Mine in den SEC Berichten grossspurig über Jahre behauptet: Annual Report 1999:
Our work schedule for the talc mine calls for an accelerated drive to commercial production in 2001, subject to our being able to obtain financing for the development of the deposit
Annual Report 2000
The construction of the talc mine is scheduled for completion in late 2001
Annual Report 2001
The construction of the talc mine is scheduled for completion in 2002.
Annual Report 2002
Mine construction, which began in August 2000, is scheduled for completion in 2003, at which time talc production is scheduled to commence
Annual Report 2003
Mine construction, which began in August 2000, is scheduled for completion in 2004, at which time talc production is scheduled to commence
Annual Report 2004
Mine construction, which began in August 2000, is scheduled for completion in 2003, at which time talc production is scheduled to commence.
Annual Report 2005
Mine construction, which began in August 2000, is scheduled for completion in 2003, at which time talc production is scheduled to commence In January 2005 the Company’s subsidiary Rozmin s.r.o. was notified that the concession regarding the Talc deposit had been cancelled by the Slovakian Government for unspecified and dubious reasons. At this point therefore no further concession is held by Rozmin www.sec.gov Wieviel Hat Eurogas in die Mine invstiert? Der Betrag dürfte sich wohl im 5-Stelligen Bereich bewegen. Denn man hat ja so gut wie nichts gemacht und im Jahre 2001 die Arbeiten eingestellt. Wie genau soll einem Unternehmen Schaden entstehen wenn sie aus "Kapitalmangel" die angekündigten Arbeiten nicht ausgeführt hat? |