The BBPK Project is suitable for an open-cut contract mining operation that will extend the
pit along strike from the adjacent mined out block. Production from the adjacent block was in
excess of 25,000 tonnes per month and Fireside is contracted to maintain a similar
productivity (300,000 tpa), mining conditions are expected to be similar to that in the existing
mining operations.
Crushing will take place onsite by use of a mobile crushing unit installed near to the BBPK
operation. A suitable crushing unit has been sourced by Fireside and is expected to be
operational by April 2010. Transportation of coal will be by road, approximately 50kms to the
Sungei Putting port facility along the Barito River, where coal will be stockpiled and sold FOB
Barge.
3m
Dann hoffe wir mal, dass der Termin eingehalten wird und der mobile Crusher einsatzbereit ist.