Semafo meldet Ergebnisse für Q2/18
Second Quarter 2018 - in Review • Gold production of 45,700 ounces compared to 47,600 ounces for the same period in 2017
• Gold sales of $58.5 million compared to $59.3 million for the same period in 2017 • All-in sustaining cost1 of $1,103 per ounce sold compared to $1,074 for the same period in 2017
• Cash flows from operating activities2 of $15.8 million or $0.05 per share1 compared to $23.6 million or $0.07 per share1 for the same period in 2017 • Adjusted net loss attributable to equity shareholders1 of $6.3 million or loss of $0.02 per share1 compared to adjusted net loss1 of $2.9 million or loss of $0.01 per share1 for the same period in 2017
• Underground mining services contract signed with AUMS for Siou Underground • Osaanpalo Zone at Boungou Proximal returns up to 17.17 g/t Au over 3.0 meters • Baali Zone at Boungou Regional returns up to 7.58 g/t Au over 9.4 meters
Boungou Mine As at June 30, 2018: • First gold poured on June 28, 2018
• Construction and commissioning of the mine 100% complete
• Construction capital expenditure on budget
• Pre-stripping of the projected 18 million tonnes complete • Construction completed with 5.6 million man-hours (18 months) without lost-time injury