October • Completion of an interpretation of the Pioneer Dome structural setting and controls of lithium caesium-tantalum (LCT) pegmatite emplacement • Receipt of assays from the Resource extension drill programme
November • Completion of the Dome North Mineral Resource update
December • Completion of the Pioneer Dome Lithium Project Scoping Study • Receipt of non-binding expressions of interest from parties seeking a financing and off-take partnership to assist with advancing the Pioneer Dome Lithium Project into production.
Ongoing Exploration activities will continue in parallel with the above key milestone activities, focused on discovering new spodumene-bearing pegmatites at the Pioneer Dome Lithium Project. |